Working Standards

  • We work to standards and control measures higher than those set out by the HSE.
  • We take photographs of initial site attendance, site set up and completed works in order to prove the standard of controls we have put in place.
  • We use photographic evidence boards on-site in order to prove control measures have been implemented.

Standard Control Measures on Asbestos Removal Projects

  • Controlled Entry Point
  • H-Type Vacuums
  • Negative Pressure Unit
  • 1000 Gauge polythene and 3inch PCL tape in order to form an airtight enclosure

SCI Asbestos Complaint Protocol

Complaints of Damage:

  • Initial response within 4 hours
  • Evidence investigated
  • Formalised reply 48 hours based on evidence gained from site

Complaint of Dust and Debris:

  • Escalated to operations director with immediate effect
  • Response within 1 hour
  • Site attendance within 24 hours (less wherever possible)
  • Pictures taken on arrival
  • Swab tests undertaken
  • Dust debris cleaned regardless of fault
  • Air test to follow if required by client
  • Investigated by SCI